School project update given at WAEDF

Image
Body

The Weatherford Area Economic Development Foundation hosted a meeting Wednesday where Joe D. Hall Construction LLC. staff spoke about the projects they are currently working on in Weatherford.

Two of the projects Joe D. Hall has been working on are the Weatherford Public School’s new East and West elementary school buildings.

“One of the big things the new buildings will acquire is new sinks which have the soap dispenser, sink, and hand dryer all in the same device. Another thing we are aiming for is security and access control. This has become a huge part of what is wanted in the new school buildings, as a parent I want to know kids are safe in school” Joe D. Hall Project Manager Shawn Bonner said.

The two new Weatherford Elementary schools are expected to be completed in fall of 2022.

Along with the new school buildings Joe D. Hall will be responsible for the construction of the new Weatherford Police Department.

“We are supposed to be provided with the design plans, when we get the design plans it will be about 6 months until we start moving dirt. After the dirt has been moved it will take about a year before the building is finished,” Joe D. Hall Representative Kris Richardson said.